Baltic Cable

From Infogalactic: the planetary knowledge core
Jump to: navigation, search
Baltic Cable
Pylons of the Baltic Cable HVDC in Sweden
Pylons of the Baltic Cable HVDC in Sweden
Location
Country Sweden, Germany
Coordinates Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
From Lübeck-Herrenwyk
To Arrie
Ownership information
Partners E.ON Sverige, Statkraft Energi
Operator Baltic Cable AB
Construction information
Manufacturer of conductor/cable ABB
Manufacturer of substations ABB
Commissioned 1994
Technical information
Type submarine cable / overhead line
Type of current HVDC
Total length Lua error in Module:Convert at line 1851: attempt to index local 'en_value' (a nil value).
Number of transmission towers 40
Power rating 600 MW
AC Voltage 380 kV
DC Voltage 450 kV
Number of poles 1
Number of circuits 1
File:Baltic Cable in Sweden.png
Track of the overhead line section of Baltic Cable in Sweden

The Baltic Cable is a HVDC power line running beneath the Baltic Sea that interconnects the electric power grids of Germany and Sweden.

The Baltic Cable uses a transmission voltage of 450 kV – the highest operating voltage for energy transmission in Germany. The total project cost was 2 billion SEK (US$280 million), and the link was put into operation in December 1994. With length of 250 kilometres (160 mi), it was the second longest high voltage cable on earth, until Basslink came into service in 2006. It is a monopolar HVDC system with a maximum transmission power of 600 megawatts (MW).

Route

Lua error in package.lua at line 80: module 'strict' not found. Lua error in package.lua at line 80: module 'strict' not found. The course of the Baltic Cable starts in Germany at the converter station at Lübeck-Herrenwyk, which is on the site of a former coal-fired power station at Lua error in package.lua at line 80: module 'strict' not found.. It crosses the river Trave in a channel 6 metres (20 ft) below the bottom of the river and then follows its course as sea cable laid at the Eastern side of this river. After crossing the peninsula at Priwall the cable runs at first parallel to the coast of Mecklenburg-Vorpommern, in order to turn behind Rostock north-easterly toward Sweden.

Approximately at Lua error in package.lua at line 80: module 'strict' not found., it crosses the submarine cable of HVDC Kontek. This is the only crossing of two submarine HVDC cables in the Baltic Sea and one of the only few worldwide.

From the landing point at the southern coast of Sweden at Lua error in package.lua at line 80: module 'strict' not found., the Baltic-Cable runs a further 5.5 kilometres (3.4 mi) as an underground cable until a point east of the road E6 at Lua error in package.lua at line 80: module 'strict' not found., where inside a fenced area the transition from underground cable to overhead powerline takes place. From there the powerline runs as overhead line over two suspension pylons in north-northwesterly direction until the first strainer at Lua error in package.lua at line 80: module 'strict' not found.. There the line turns into north-northeasterly direction and runs over seven suspension pylons past Södra Häslov to the next strainer at Lua error in package.lua at line 80: module 'strict' not found.. Its track goes now further on 8 suspension pylons in northeasterly direction to the third strainer at Lua error in package.lua at line 80: module 'strict' not found.. The next section consists of 15 suspension pylons from which the third tower situated at Lua error in package.lua at line 80: module 'strict' not found., the ninth tower situated at Lua error in package.lua at line 80: module 'strict' not found. and the 12th tower situated at Lua error in package.lua at line 80: module 'strict' not found. are angle suspension pylons. It ends at a strainer east of Västra Ingelstad at Lua error in package.lua at line 80: module 'strict' not found.. From this strainer the line runs on one suspension pylons, one angle suspension pylon situated at Lua error in package.lua at line 80: module 'strict' not found. and the termination tower in northeasterly direction to Kruseberg converter station at Lua error in package.lua at line 80: module 'strict' not found.. This facility, which is also known as Arrie converter station, is attached to a 400 kV/130 kV substation of the Swedish power grid.

File:Balkab1.jpg
Kruseberg converter station on the Swedish side of the Baltic Cable HVDC interconnection

The total count of pylons of the 12.1-kilometre (7.5 mi) long overhead line is 40. All these pylons have a single crossbar, on which two conductors are mounted on 6-metre (20 ft) long insulators. Each conductor is a bundle of two ropes with 910 mm2 cross section. Both conductors are connected with each other at the ends of the overhead line, so this line is unipolar, although it looks bipolar.

The anode, which is situated in the Baltic Sea at Lua error in package.lua at line 80: module 'strict' not found. consists of 40 titanium nets each with a surface of 20 m2, which are laid on the sea bottom under plastic tubes and stones. It is connected to Kruseberg converter station with a 23-kilometre-long underground and submarine power line, which consists of two parallel-connected XLPE-insulated cables with 630 mm2 cross section, entering the Baltic Sea at Lua error in package.lua at line 80: module 'strict' not found. and at Lua error in package.lua at line 80: module 'strict' not found..

The cathode is situated in the Baltic Sea north of Elmenhorst at Lua error in package.lua at line 80: module 'strict' not found.. It consists of a bare copper ring with a 2-kilometre diameter. It is connected to the static inverter plant in Lübeck-Herrenwyk with a 32-kilometre-long XLPE-insulated cable. The first 20 kilometres of this cable have a cross section of 1400 mm2 and the last of 800 mm2. This cable is laid in the tunnel under Trave River close to the high voltage cable and from then until a point situated at Lua error in package.lua at line 80: module 'strict' not found. in a distance of 2.5 metres to the high voltage cable. By this the magnetic field, which may affect compasses of vessels in this highly frequented area is reduced. The remaining way to the cathode it runs on a separate way. As Baltic-Cable is a monopolar line it produces much higher magnetic fields than bipolar cables with the same ratings.

Operation

Because this overhead line can generate radio interference, there is a highly effective active filter system installed at the Kruseberg converter station. In the Lübeck-Herrenwyk converter station, there is no requirement for such a system, because there is no overhead powerline section on the German side.

The cable cannot be operated at the maximum transmission rating of 600 megawatts, because the 380 kV line which begins at the converter station of Lübeck-Herrenwyk ends at the Lübeck-Siems substation. This is the only 380 kV powerline in Germany, which has no direct connection to the Central European 380 kV grid, which causes the Baltic Cable to have a 372 megawatt (MW) capacity instead of 600 MW.[citation needed] From there power flows on 220 kV and 110 kV lines, which reduces the maximum transmission rate and increases the losses of the transmission.

In the area of the converter station there is also a 110 kV/220 kV sub-station, fed by two 110 kV circuits from the Lübeck-Siems sub-station. There is no transformer for coupling the 380 kV- and the 110 kV-grid in the area of the Lübeck-Herrenwyk converter station.[citation needed]

Expansion schemes

Of the two originally planned 380 kV lines to Lübeck (from Krümmel Nuclear Power Plant to Lübeck-Siems and from Schwerin substation to Lübeck-Herrenwyk), the 380 kV line between Krümmel and Lübeck-Siems was canceled according to speakers from E.ON AG.

There is still the option to build a 380 kV line from Lübeck to another 380 kV substation in Schleswig-Holstein, Hamburg or Lower Saxony. The construction of the 380 kV link between Lübeck-Herrenwyk and Schwerin is not progressing due to opposition from ecologists.

A transmission rating of 600 MW should be possible via a new 220 kV cable and a static var compensator in Lübeck-Siems after 2005.

Sites

Site Coordinates
Kruseberg HVDC converter station Lua error in package.lua at line 80: module 'strict' not found.
Västra Värlinge Cable Terminal (Sweden) Lua error in package.lua at line 80: module 'strict' not found.
Herrenwyk HVDC converter station Lua error in package.lua at line 80: module 'strict' not found.

See also

External links

Lua error in package.lua at line 80: module 'strict' not found.