EASSy

From Infogalactic: the planetary knowledge core
(Redirected from EASSy (cable system))
Jump to: navigation, search
EASSy (Eastern Africa Submarine Cable System)
Cable map18.svg
Landing points
<templatestyles src="Plainlist/styles.css"/>
Total length 10,000 km[1]
Design capacity more than 10 Tbit/s[1]
Technology Fiber optics
Date of first use July 16, 2010 (2010-07-16)

The Eastern Africa Submarine Cable System (EASSy) is an undersea fibre optic cable system connecting countries in Eastern Africa to the rest of the world.

EASSy runs from Mtunzini in South Africa to Port Sudan in Sudan, with landing points in nine countries and is connected to at least ten landlocked countries — which will no longer have to rely on satellite Internet access to carry voice and data services.

EASSy is the highest capacity system serving sub-Saharan Africa, with more than 10 terabit per second (Tbit/s), 2 fibre-pair configuration.[1] It is the first to deliver direct connectivity between east Africa and Europe / North America. It is the only system with built-in resilience end-to-end. EASSy interconnects with multiple international submarine cable networks for onward connectivity to Europe, the Americas, the Middle East and Asia.

The project, partially funded by the World Bank, was initiated on January 2003, when a handful of companies investigated its feasibility. The cable entered service on 16 July 2010,[2] with commercial service starting on 30 July 2010.[3]

Project milestones

  • MoU signature – December 2003
  • Detailed feasibility study – March 2004
  • Data gathering meeting – June 2005
  • C&MA drafting finalization – March 2006
  • Supply contract award – September 2006
  • Registration/incorporation of SPV – January 2007
  • Construction and maintenance agreement (Shareholders' Agreement) Signature (C&MA) – 12 October 2006 to 12 February 2007
  • Financial closure – March 2007
  • Supply contract signature – March 2007
  • Construction Started – March 2008
  • Cable manufacture complete – November 2009
  • Marine laying commencing – December 2009
  • Construction complete – April 2010
  • Live – July 2010

Telecommunications companies of participating nations

Cable landing points

The cable landing points are:[4]

See also

References

  1. 1.0 1.1 1.2 Lua error in package.lua at line 80: module 'strict' not found.
  2. WIOCC-EASSy fibre cable goes live
  3. EASSy enters commercial service
  4. EASSy network topology

External links