Inga–Shaba HVDC

From Infogalactic: the planetary knowledge core
(Redirected from Inga-Shaba)
Jump to: navigation, search
Inga–Shaba EHVDC
File:HDVC Inga-Shaba.png
Route of the Inga–Shaba EHVDC in Democratic Republic of Congo
Location
Country Democratic Republic of Congo
Coordinates Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
Lua error in package.lua at line 80: module 'strict' not found.
From Inga hydroelectric complex
To Shaba (Katanga)
Ownership information
Operator Société nationale d'électricité (SNEL)
Construction information
Contractors Morrison-Knudsen International, ASEA, Sadelmi-Cogepi, Irish GE subsidiary
Commissioned 1982
Technical information
Type overhead line
Type of current HVDC
Total length Lua error in Module:Convert at line 1851: attempt to index local 'en_value' (a nil value).
Power rating 560 MW
DC Voltage +/-500 kV
File:HVDC Inga Shaba.GIF
Single Line Diagram of Inga-Shaba HVDC

The Inga–Shaba EHVDC Intertie (officially: The Inga–Shaba Extra High Voltage D.C. Intertie; nickname: Inga–Shaba and also referred to as Inga–Kolwezi) is a 1,700 kilometres (1,100 mi)-long high-voltage direct current overhead electric power transmission line in the Democratic Republic of Congo, linking the Inga hydroelectric complex at the mouth of the Congo River to mineral fields in Shaba (Katanga).[1] It was primarily constructed by Morrison-Knudsen International, an American engineering company, with the converter equipment supplied by ASEA. Construction was completed in 1982 and it cost US$900 million. The scheme was, for many years, the longest HVDC line in the world.

History

The Inga–Shaba HVDC represented one of the United States' most important third world commitments of the 1970s and 1980s. However, construction progress was plagued by rebel insurgency in Southern Zaire, massive logistical challenges, large cost overruns, and financing delays.

By utilizing the hydroelectric potential of the Inga Dam and by constructing one switching station near Kinshasa at Selo, the Government of Zaire under Mobutu Sese Seko was theoretically able to control the flow of power to secession-prone Katanga, then Shaba, province, but never actually exercised this option. It was reported in La Libre Belgique, a Brussels newspaper, that Tractionel, a Belgian electrical contractor, had argued that more economical alternatives were available nearer Shaba, using low-head generator plants, but had been overlooked in favor of the American consortium, consisting of Morrison-Knudsen International as a prime contractor, and Swedish ASEA, Italian Sadelmi-Cogepi and Irish GE subsidiary as sub-contractors.

The project was initially conceived as a US$250 million contract - but cost overruns, partly due to unanticipated armed conflict in Shaba Province, pushed the final price up over US$1 billion, with unofficial estimates ranging as high as US$1.3 billion, inclusive of a comprehensive Operations and Maintenance Contract.[2]

Construction of the Inga–Shaba Project provided the Ministry of Energy and the Société nationale d'électricité (SNEL), with the means to promote further development activity throughout Zaire, by attracting potential investors and overseas firms; however, there have been suggestions that well-placed officials in the Mobutu government may have accepted gratuities at various critical junctures during the construction phase.[3] As the Republic became more indebted to overseas financial entities, the Inga–Shaba Project ultimately accounted for approximately 20% of the former Zaire's debt burden, the total amount of which was $5 billion at the time, according to a variety of credible sources.

Route

The ten-year project entailed design and construction of a 1,700-kilometre (1,100 mi) electrical transmission line from Inga (Lua error in package.lua at line 80: module 'strict' not found.) at the mouth of the Congo River, specifically from the Inga Dam, one of Africa's three largest hydroelectric complexes, to the distant copper mining region then known as Shaba, today Katanga. It featured switching stations at Selo (near Kinshasa) (Lua error in package.lua at line 80: module 'strict' not found.), Kikwit (Lua error in package.lua at line 80: module 'strict' not found.), Kananga (Lua error in package.lua at line 80: module 'strict' not found.) and Kamina(Lua error in package.lua at line 80: module 'strict' not found.), prior to delivering power to the Kolwezi Inverter Station(Lua error in package.lua at line 80: module 'strict' not found.).[4]

Electrodes

The electrode for the Inga static inverter plant is situated 39 kilometres away from the station at Lua error in package.lua at line 80: module 'strict' not found. and designed as linear ground electrode with a resistance of 0.24 Ohms, while the electrode of Kolwezi static inverter plant, which is situated 11 kilometres away from the station at Lua error in package.lua at line 80: module 'strict' not found. is designed as three-legged ground star electrode with a resistance of 0.14 Ohms.

Technology

This scheme, equipped from the outset with thyristor valves provided by Swedish subcontractor ASEA, was designed to transmit 560 megawatts, in the first phase, at a symmetrical bipolar voltage of ±500 kilovolts. Although not the first 500 kV HVDC project in operation (the ±533 kV Cahora Bassa scheme having been completed in 1977) it was the first such scheme to use only a single twelve-pulse bridge per pole. Consequently its thyristor valves were the highest-rated in the world (in terms of voltage) at the time and remained so until the completion, in 2007, of the ±450 kV, single-converter NorNed scheme.[5] The thyristor valves for Inga Shaba had 258 thyristors in series in each valve and were air-insulated and air-cooled.[1]

Inga Shaba was the longest HVDC transmission line in service until 2010, when it was overtaken by the 2071 km, ±800 kV, 6400 MW HVDC link from Xiangjiaba Dam to Shanghai in China. Because the line runs through relatively inaccessible terrain, an unusually broad right-of-way was cleared, at considerable expense, to ensure tower integrity.

The line operated initially at only 10% of capacity. In the 1990s, prior to major social unrest, the line increased its power transmission to 200 MW, still considerably below design capacity. As of 2000, reliability had been poor with many thyristor failures at the inverter station.[6] As of 2010, the line was still functional as far as Bandundu, the capital of Bandundu province, approximately 400 kilometres (250 mi) northeast of Kinshasa.[citation needed] In 2009 ABB was awarded a contract to refurbish and modernise the converter equipment. This upgrade is due to be completed in 2013.

See also

References

  1. 1.0 1.1 Compendium of HVDC schemes, CIGRÉ Technical Brochure No. 003, 1987, pp136-141.
  2. U.S. State Department, Zaire Desk, circa 1985
  3. Nzongola-Ntalaja, G., 2002, and Kwitny, J.,1984
  4. Technical Reports, MKI, 1975-1985
  5. Skog, J.E., van Asten, H., Worzyk, T., Andersrød, T., Norned – World’s longest power cable, CIGRÉ session, Paris, 2010, paper reference B1-106.
  6. Oliveira,H., Sintra,L., Lokala,J., Pembele,I.E., Lubini,I.E.., Goossen,P.V., Bhana,S., Operating experiences in the HVDC systems of the Southern African power pool Cahora-Bassa: Apollo and Inga-Shaba, CIGRÉ session, Paris, 2000, paper reference 14-111.

Bibliography

  • Kwitny, Jonathan Endless Enemies: The Making of an Unfriendly World (1984; ISBN 0-14-008093-7)

Nzongola-Ntalaja, Georges. The Congo from Leopold to Kabila: A People's History. New York: Zed Books, 2002.

External links