The West Africa Regional Rail Integration is a proposal to connect up isolated railway networks in West Africa.

Overview

In 2009, USTDA approved funding of $750,000 for a feasibility study grant to assist the Union économique et monétaire ouest-africaine (UEMOA), in determining the technical and economic viability of developing a rail line from Bamako, Mali to Mali's southeastern border with Côte d’Ivoire, as well as its associated costs, design and construction criteria, and implementation plan. The study will also include a technical assessment on the existing rail line between Dakar, Senegal and Bamako, which would be linked to the proposed rail line. The total cost of the proposed line is expected to exceed $1.9 billion.

The 15-month railway study USTDA contract was authorized to begin in October 2010. ZETA-TECH Associates of Cherry Hill NJ (NOW Harsco Rail Intelligent Solutions) undertook the study with other companies assisting, including the Law Offices of Peter C. Hansen, LLC, which analyzed the existing legal framework and drafted a treaty to modernize the ownership structure and facilitate long-term financing of the revitalized railway. A final report was delivered in December 2012, and a French translated copy was accepted by UEMOA in March 2013.

Timeline

2011

No progress reported on that announcement as of the summer of 2012

In October 2012 UEMOA held a meeting to at its Burkina Faso headquarters to review and discuss the initial draft final report of the USTDA funded rail project. The consulting team presented four different capital cost modernization plans. One would be for just minimum safety changes. The most forward would support a possible 10 million ton modernized standard gauge conversion rail project—with the earliest train operations occurring sometime around 2017 between Dakar and Bamako. The requirements would include an integrated plan execution with mine + rail + port + a new Railway 2-nation Authority—if the project consultant suggestions are followed. Building just the railway without integrating these other transport and customer commercial actions was recommended as a critical process for moving towards a final total plan.

The Bamako to the south railway corridor has a separate set of competitive issues and technical costs associated with it.

No public policy decision for either of the two railway corridors is likely until sometime in 2013 given the complexity of the choices and critical action items in order to move forward.

The consultant team also projected the possible Pro Forma Income Statement for three of the possible railway operating company levels of modernization. Contact UEMOA or the consultants for further information as to the capital costs, possible operating scenarios, and economic outcomes.

A complete Critical Path for debating and then making project decisions (given the many technical choices) and then executing project funding and bidding and construction was also submitted to UEMOA by the consultant team. As of mid October 2012 that process was just starting at a technical review level under the guidance of UEMOA staff.

A PowerPoint presentation that summarized the technical results and possible financial or Pro Forma operating income of the upgraded Dakar to Bamako railway was presented to The Corporate Council of Africa in Washington in mid-February 2013. Among the items discussed was the calculated cost of 1) a modern meter gauge railway service as requested by a UEMOA rail task force "solution" and 2) the cost of a conversion to a standard gauge between Dakar and Bamako. The project capital costs together with the estimated cost of rail operation plus the cost of repaying the capital infrastructure debt were identified in a Pro Forma Income Statement for the improved railway enterprise (a designed railway company) at a given future year 2017 tonnage. The project design was built around an attempt to resolve for the lowest possible bulk cargo rates to reach a new proposed bulk cargo port south of Dakar. The target rate was <$32 a metric ton at standard gauge and somewhat higher at meter gauge. This pro forma analysis shows evidence that the railway can be independently financed by investors without the need of a Senegal or a Mali mine company actual railway "ownership" (a burden to the mine company Balance Sheet). A railway authority is recommended as a means of attracting private capital using the bonding and commercial structure of such a government of Senegal and Mali chartered body rather than a conventional concession approach. The railway feasibility was based on a variety of engineering and economic possible designs that used different rail mode market shares and different levels of railway operating efficiency (operating ratios) and different track structure safety standards. Naturally, the local African leaders will have to make the final design choices. From an economic point of view, subsidies and doners are not necessary if the traffic market share and the engineering and train operational designs are correctly matched. USTDA financed The next step is for the large shippers to meet collectively or individually with UEMOA and test the feasibility study against their specific (and often private) shipper requirements. Either the authors or UEMOA should be contacted. In the meantime, rail service is continuing in the corridor under the existing concession arrangement.

During February 2013 the report was translated into French. Contact UEMOA or Harsco Rail Zeta Tech or USTDA for further information.

[2] Jim Blaze Project Director

2014

2015

  • Construction starts on extension of railway in Benin to Niger. [4] Both are 1,000 mm (3 ft 3 38 in) gauge. The existing railway in Benin will be upgraded.