Western HVDC Link
From Infogalactic: the planetary knowledge core
Western HVDC Link | |
---|---|
Location | |
Country | United Kingdom |
From | Hunterston, Scotland |
Passes through | England |
To | Flintshire Bridge, Wales |
Ownership information | |
Partners | National Grid plc ScottishPower Transmission |
Construction information | |
Manufacturer of conductor/cable | Prysmian |
Installer of conductor/cable | Prysmian |
Installer of substations | Siemens |
Construction started | 2013 |
Expected | 2016[1] |
Technical information | |
Type | Submarine power cable |
Type of current | HVDC |
Total length | Lua error in Module:Convert at line 1851: attempt to index local 'en_value' (a nil value). |
Power rating | 2,200 MW[1] |
DC Voltage | 600 kV |
The Western HVDC Link is a high-voltage direct current (HVDC) electricity link currently under construction between Hunterston in western Scotland and Flintshire Bridge (Connah's Quay) in North Wales. It has a transmission capacity of 2,200 MW, and is expected to cost €1.1bn.[2]
It consists of 422 kilometres (262 mi) of cable, of which 385 kilometres (239 mi) is underwater.[1] It is the first subsea 600kV link.[3]
There are two cables, which in shallow water are laid in a paired bundle, and in deep water laid about 30 metres apart, generally buried about 1.5 metres below the seabed. The cables are jointed in 120 km sections.[3]
References
External links
- No URL found. Please specify a URL here or add one to Wikidata.
<templatestyles src="Asbox/styles.css"></templatestyles>
<templatestyles src="Asbox/styles.css"></templatestyles>